Motihari-Amlekhgunj pipe laying process completed 70pct - NOC- The 20th China (Guangzhou ) Int’l tube & pipe Processing Equipment Exhibition
9/13/2018  管材展-钢管展-steel tube expo-tube &pipe expo
---------------------------------------------------------------------------------------------------------------
    The Himalayan Times reported that almost 70 per cent of the pipe laying process of the much-hyped Motihari-Amlekhgunj Pipeline Project has been completed so far, according to Nepal Oil Corporation (NOC). While pipes have been laid at majority sections of the project’s route in Simara and Gandak Chowk and Bypass Road of Birgunj, works are underway to lay pipes along the project’s route in Pathlaiya, Jitpur and Parwanipur, informed Mr Birendra Goit, spokesperson for NOC.

Mr Goit said that “The pipe laying process has not been started especially along different conserved areas. We will begin to lay pipes along these areas once the environmental impact assessment (EIA) of the oil project is completed.”

Once the pipe laying process is completed, works regarding development of fuel pumping stations and injecting fuel tanks, among others will be carried out as per NOC.

He said that “The pipe laying process was hampered due to the unfavourable monsoon for a few months. However, the construction works of the project have been expedited now.”

The cross-border pipeline project stretches almost 69 kilometres. Of the total length, 32.7 km falls in Indian territory while 36.2 km falls in the Nepali territory.

The project involves laying pipeline of 10.75-inch diameter and will have the capacity to supply 200,000 litres of fuel per hour, with fuel pumping facilities in Motihari on the Indian side.

The pipeline project, which was signed between Nepal and India in August 2015, states that both NOC and Indian Oil Corporation (IOC) will together complete the project within designated timeframe of 30 months from the date of receipt of statutory clearances.

As NOC claims that the actual construction works (pipe-laying process) of the project began from April 17, the project is expected to be completed within mid-October 2020. 管材展-钢管展-2019广州国际管材及管材加工设备展-中国展出效果最好的管材展-巨浪展览 - The 20th China (Guangzhou ) Intl tube & pipe Processing Equipment Exhibition -Tube exhibition, Tube expo,2019 Tube exhibition,2019 Tube expo, China Tube exhibition, China Tube expo, pipe exhibition, pipe expo, 2019 pipe exhibition,2019 pipe expo, China pipe exhibition, China pipe expo, Guangzhou pipe exhibition, Guangzhou tube exhibition, Guangzhou pipe expo, Guangzhou tube expo 