voestalpine successfully finishes repairs to the large blast furnace at the site in Linz—The 20th China(Guangzhou)Int’l Heat Treatment, Industrial Furnace Exhibition
9/29/2018  热处理展-工业炉展-heat treatment expo-furnace expo
---------------------------------------------------------------------------------------------------------------
    Completing the general renovation of Blast Furnace A has brought the voestalpine Steel Division a further step towards increasing energy and resource efficiency at its steel production site in Linz. After a 111-day period for repairs, the furnace, in which two-thirds of the entire annual pig iron volume of five million tons is produced, today successfully restarted operations. At a total cost of around EUR 180 million, the so-called relining project involved completely replacing the extremely wear-resistant interior lining of the blast furnace, as well as modernizing all other facilities used in operating the blast furnace. At around the same time, interim repairs were carried out on one of the two blast furnaces in Leoben-Donawitz.

The comprehensive upgrades to Blast Furnace A are important in safeguarding the future of the site in Linz, and that of its about 11,000 employees, for the coming decade. At the same time, the high technical standard of this blast furnace is also the basis for supplying our processing sites with high-quality steel grades.

While modernizing Blast Furnace A we upgraded all the process steps to the state-of-the-art in order to achieve even better results in terms of resource conservation and material consumption. We are doing this by using completely new digital capabilities as well.

The applied technologies include 3D radar to determine the optimum distribution of raw materials and automated temperature measurements within the blast furnace. Around 160 employees in the core voestalpine team worked to prepare and realize this major project, while at the same time a total of 1,000 people were employed at the site for over a year. Special simulation software which mapped all the plant and equipment as well as process scenarios was used to plan the relining. In future this tool will also be used during ongoing operations at the blast furnace.

Parallel to the major project in Linz, one of the two blast furnaces belonging to the Metal Engineering Division in Leoben-Donawitz also underwent interim repairs. After 64 workdays, the furnace, which is responsible for around half of the 1.5 million tons of annual pig iron production at the Styrian site, returned to normal operations this week. The costs for the repairs, which are routinely undertaken on each of the two furnaces at the site once every four years, amounted this time to the comparatively low sum of EUR 14 million. 热处理展-工业炉展-2019第二十届广州国际热处理、工业炉展览会-中国效果最好的热处理工业炉展--巨浪展览 —The 20th China(Guangzhou)Int’l Heat Treatment, Industrial Furnace Exhibition -Heat Treatment exhibition, Heat Treatment expo, 2019 Heat Treatment exhibition, 2019 Heat Treatment expo, China Heat Treatment exhibition, China Heat Treatment expo, Industrial Furnace exhibition, Industrial Furnace expo, 2019 Industrial Furnace exhibition, 2019 Industrial Furnace expo, China Industrial Furnace exhibition, China Industrial Furnace expo